Riverside Works
Attention required
Last updated: Today at 09:30
↻ Refresh
Generate report
Client
Hembury Developments
Role
Employer's Agent
Stage
Construction stage
Contract
JCT Standard Building Contract with Quantities (SBC/Q)
Contractor
Meridian Construction Ltd
Contract sum
£2,850,000
Approved budget
£2,950,000
Start on site
3 March 2026
Contract completion
14 November 2026
Cost position
−£104k
Favourable, against approved budget
Programme position
+11 days
Behind plan
Key risks
3
1 critical
Decisions required
4
2 due this month
Information required
7
Open items
What changed this period
Steelwork package awarded
Confirmed saving of £142k against package allowance.
MEP coordination cost increase
Additional £38k anticipated for acoustic enclosure works.
Programme delay increased
Weather impact and late information from utility provider.
Registers
Risks
3
Decisions
4
Actions
5
Information required
7
Construction changes
3
REPORT DRAFT READY
Monthly report — Jul 2026
Monthly report draft ready for professional review.
Review report →